Location: Mirzaye Shirazi St., (Nejatollahi), Tehran
Final Year: 2011-2012
Build System: Hybrid Steel Structure Combined with LSF System
Infrastructure: 22000 m²
Employer: OB-GYN Department Yas Hospital
Duration of Execution: 8.5 months
Floors: 9
Building Use: Hospital
Activity: Excavation and nailing operations, construction of the steel superstructure, composite slab system, and retaining walls for the 200-bed Moheb OB-GYN Department of Yas Hospital