گروه مهندسی سی بن سازه مهر

Temporary Housing of Arg-e Bam

Location: Bam
Final Year: 2004-2005
Build System: LSF System
Infrastructure: 50000 m²
Building Use: Residential
Activity: Contractor

Following the tragic Bam earthquake in February 2004, Cibonsazeh Company initiated the Temporary Housing Project, providing a rapid-deployment housing solution.
The company designed and constructed prefabricated modular units that were utilized across Bam and the designated surrounding areas.

The system employed lightweight prefabricated materials, allowing for the production of 50 housing units (each 24 m²) per day in Tehran. Each unit was assembled and made functional in Bam in less than 30 minutes, resulting in the completion of a total of 3,000 units.